Installations for turning to account the gas reserves
Project: Surface installations aimed to turn to account the natural gas reserves, inclusive of gas gathering pipes, main gathering group, gas dehydration unit, pipeline structure, fiscal gas metering station. Project type: EPCM Scope of work: Basic and detailed design, procurement and supply of construction materials, erection works (mechanical, electrical, instrumentation, protection, insulations, paintings), tests, commissioning and project management. Inspet role: Main Contractor Execution period: Oct 2008 - Nov 2009 |
|
![]() |
![]() |