Gas underground storage
Project: Surface installations for oil production units, crude oil pipelines from the drilling rigs to the groups, gas gathering pipelines between the groups and the main unit, measuring installations. Project type: ECPM Inspet role: Main Contractor Project aim: Increasing the natural gas underground storage capabilities as of the national gas system. Scope of work: Basic and detailed engineering, procurement and supply of pipes and equipment, erection works (excavations, pipelines welding and installation of more than 160 km, mechanical, electrical, instrumentation, protection, painting), tests, commissioning, project management Execution period: July 2007 - September 2010 |
![]() | ![]() |
![]() |